TOTAL AROMATEN Shut-down

ADF TIB has its first shut-down behind the back at TOTAL OLEOFINS ANTWERP.

After months of preparation was in september 2015  started with the turn around of the aromatics plants. 5 phases of intensive work were carried efficient out by the ADF staff . Multiple disciplines came to bid, such as piping, mechanics, coax heat exchangers and mounting.
After a successful shutdown we are proud to mention that 10,000 man hours were performed without accidents.

 

Related cases